Proposition
Our most frequent challenge is to meet ever shortening timescales, so the task was laid down to find ways of building quicker, smarter and more intelligently but without cost implication.
Ken Hall - Senior Vice President Design and Construction Europe, ProLogis UK
Philosophy
High bandwidth:
Windows Media  Quicktime
Low bandwidth:
Windows Media  Quicktime
Video Question? Click here
We call this building a smart building. We are constantly seeking to provide competitive advantage to our clients. They're the guys who really make our business move and when we find advantage for them we find it for ourselves."
Ken Hall - Managing Director, Global Development, ProLogis UK
"One of the major issues of the construction industry is time. This is our way of cutting that time scale down and meeting a client need."
David Mills - Project Manager Services, ProLogis UK
"In the past we have been doing buildings of this scale on 26 weeks."
Richard Butler - Site Manager, Winvic
"From a clients perspective we can actually give the client the building that they require in a 10 week period as opposed to building something speculatively and then having to re-jig the internals of it to make it work for their scheme."
Fergie Taylor, Vice President Commercial, ProLogis UK
Fergie Taylor, Vice President Commercial, ProLogis UK
"The customer is king. We have to do what the customer wants."
Kate Bedson - Vice President Development, ProLogis UK"
"And the result is we now have something that when we say 10 weeks we feel really confident we can do it in 10 weeks."
Ken Hall - Senior Vice President Design and Construction Europe, ProLogis UK
Apex Park, Daventry, East Midlands

Apex Park, Daventry, East Midlands

Apex Park, Daventry
ProShed: Built in flexibility

In the summer of 2004 ProShed was used for a 175,000 ft² distribution centre for JD Weatherspoon/Exel at Apex Park, Daventry. One of the features of this development was the need for a large proportion of the property to be refrigerated, requiring additional work to insulate the base and specialist construction. ProShed proved to be the ideal process. The steel work and roof took just four weeks allowing the refrigeration team to start work undercover.

The way that ProShed is managed allows the flexibility for variations from standard to be accommodated. In fact the benefits of ProShed is that it enables additional tailored solutions to be carried out more easily than when using traditional building methods.